June 26, 2015
General Information
As you may have noticed from the outside looking in, the activity on the site has changed focus over the last few weeks. We are in the final stage of the utility enabling phase at the same time we are ramping up for the building phase.
- Some interesting facts related to the Enabling phase:
- Over 20,000 lf of rigid conduit installed
- 2,100 lf of welded Chilled Water Pipe installed
- 250 X-rayed welds completed and tested
- Over 2,500 lf of Civil Piping installed (water, drain, sewer)
- Over 5,000 tons of construction waste and Building 12 debris hauled away (99% recycling rate)
- Over 2,000 lf of concrete encased piping removed from under Building 12 slab
- Over 1,000 lf of Ductbank removed
Colored lines indicate new utility services installed as designed for the enabling phase
Progress screen capture of 3D MEPFP coordination model
Progress screen capture of 3D MEPFP coordination – cleanroom chase
Progress Photos
Final connections of 30” CHW lines at Central Utilities Plant
Backfill of electrical and tel data in work zone A
New roof hydrants at Building 13
Installation of new areaway at Building 26 (work zone G)
Excavator making first cut for pre-trench scope as southeast corner