Inside MIT.nano

The MIT Corporation tours the state-of-the-art research facility taking shape in the heart of campus.

MIT.nano rising

MIT's future home for cutting-edge nanoscience and nanotechnology research gets fitted with 23 tons of steel per day.

Digging in

Workers at the MIT.nano site have reached the halfway point in the construction's excavation phase.

12/09 construction update

Since the last update in June the following work has been completed: 13,000 lineal feet of underground conduit were installed; 2,100 lineal feet of chilled water pipe were installed; 250 welds were x-rayed; 3,375 cubic yards of concrete for slurry wall were placed.