9/15 construction forecast

MIT.nano project updates will be issued on a weekly basis throughout the duration of the project and will provide a two-week look ahead outlining projected activities.

9/8 construction forecast

Interior work in Building 16: Installation of a temporary electrical feed through Building 16 will start on September 22 and continue through December 2014. Access to elevators and stairway to Building 8 will remain available during construction period.

8/29 construction forecast

Interior work in building 16: Installation of new 16” chilled water lines on level 3 started on 8/18/14 and is scheduled to be complete in early October. Working hours are 6:00am to 3:30pm. A temporary work barrier has been installed for safety. Passage between buildings 16 and 8 will be altered at level 3 and level 2 for the duration of this work scope. A detailed plan of the altered route was sent out to the MIT community last week.

8/19 construction forecast

Interior work in Building 16: Installation of new 16″ chilled water lines on level 3 started on 8/18/14 and is scheduled to be complete in October. Working hours are 6:00am to 3:30pm. A temporary work barrier has been installed for safety.

8/1 construction forecast

Passage between buildings 16 and 8 will be altered at level 3 and level 2 for the duration of this work scope. A detailed plan of the altered route will be sent out to the MIT community next week.

7/25 construction forecast

MIT.nano project updates will be issued on a weekly basis throughout the duration of the project and will provide a two-week look ahead outlining projected activities.